摘要
通过对高速铁路试验段项目路基段不同填料类型填筑工期的实际调查研究,分析计算出不同填筑层的平均工期水平,为类似项目合理的安排施工进度提供指导。
According to the research on the factual investigation over the filling construction periods with various fillers on the roadbed section of the experimental section along the express railway,the paper analyzes the average construction periods of various filling layers,so as to provide the direction for the reasonable arrangement for the construction progress of similar programs.
出处
《山西建筑》
2012年第16期150-151,共2页
Shanxi Architecture
关键词
高速铁路
路基
工期
express railway
roadbed
construction period