浅埋偏压隧道开挖顺序数值分析 被引量:1

Numerical Analysis on Excavation Sequence of Shallow-Buried Unsymmetrical Loading Tunnel
下载PDF
导出
摘要 利用平面数值模拟方法,以某浅埋偏压的公路隧道施工为背景,对隧道左右洞开挖顺序进行施工数值模拟,分析开挖过程中围岩应力的变化情况,找到两种开挖方式在整个开挖过程中最容易产生破坏的施工步骤,得出浅埋偏压隧道先开挖深埋侧可避免出现较危险的施工状态这一结论,对研究类似工程的施工具有一定的指导意义。 Based on a shallow-buried unsymmetrical loading tunnel,the paper simulates the process of left hole and right hole′s excavation by planar numerical simulation method in order to analyze the change of stress of surrounding rock,finds out the construction steps which are easiest to be damaged by the above two excavation modes during excavation,and draws a conclusion that excavating deep-buried side of the shallow-buried unsymmetrical loading tunnel first can avoid occurrence of dangerous construction state,in hope of providing a certain guidance for research on construction of similar projects.
作者 史寒冬
出处 《交通标准化》 2012年第10期109-112,共4页 Communications Standardization
关键词 浅埋偏压隧道 有限元 开挖顺序 水平侧压系数法 shallow-buried tunnel finite element excavation sequence horizontal lateral pressure coefficient method
  • 相关文献

参考文献7

二级参考文献29

共引文献3560

同被引文献5

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部