本文重点介绍了混凝土生产与温度控制、金属结构及机电设备等施工情况和关键性技术。三峡工期工程需浇筑混凝土1846万m^3,安装金属结构及机电设备埋件19.2万t,施工工期6年。
Three Gorges Project will place 28 million m3of concrete in total and install 720,000 ton of metals and re-bars. For the second stage, the project needs to place 18.46 million m3 concrete and has 192,000 ton metal works and electrical equipment installed and buried within 6 years of implementation period. The year of 2000 features in the highest construction intensity in the second stage. 5.4 million m3 of concrete is schedule to be placed with peak monthly placement of 580,000 m3 and 38,000 m3 metal works installed.