摘要 对掘进机械设备进行配套选型,依据矿井现有技术力量配备了机械化作业线,对掘进工艺进行优化,施工组织采用平行作业方式,实现了复合软岩地质条件下回采巷道的快速掘进,有效地解决了矿井接续困难的问题。 Selection and equipment was done on tunnelling machinery, mechanized operating line was equipped based on current technical force of mine, drivage technology was optimized, parallel opera- tion mode was adopted in construction organization, thus high-speed drivage of mining laneway under geo- logical condition of compound soft-rock was realized tively. , difficult mine connection problem was solved effec-
出处 《现代矿业》 CAS 2012年第5期9-11,共3页 Modern Mining
关键词 复合软岩 回采巷道 快速掘进 机械化 Compound soft-rock, Mining laneway, High-speed drivage, Mechanization