任何一道工序施工前都需要综合比较,选择简捷高效的施工方案。某工程针对山区地形条件复杂的情况,合理地选取了剪力销法盖梁施工。该文主要简述了剪力销法施工的相关验算及施工工艺,可供同行参考。
Any procedure is required to compare comprehensively before construction so as to select a simple and high-efficient construction scheme.Aiming at the situation of complex mountainous terrain,the bent cap construction by shear pin method is reasonably selected for a project.The article briefly describes the relative checking calculation and construction technology of the shear pin method,which can be referred for the similar projects.
出处
《城市道桥与防洪》
2012年第4期136-139,276,共4页
Urban Roads Bridges & Flood Control
关键词
桥梁
剪力销
盖梁
验算
bridge,shear pin,bent cap,checking calculation