新九燕山隧道主洞与辅助坑道交叉口施工技术 被引量:2

Construction Technology of Intersection between the Main Cavity and Auxiliary Tunnel in the New Jiuyanshan Tunnel
下载PDF
导出
摘要 根据包西铁路大断面红黏土隧道新九燕山隧道施工实例,就斜井和大跨度红黏土隧道交叉口施工方案进行选择,并对斜井向正洞施工方法的转化、施工技术措施等进行阐述。 This paper, taking construction of the New Jiuyanshan Tunnel, a red clay tunnel with a large section of Baoxi Railway as an instance, makes a choice of the construction program for the intersection between the inclined shaft and large- span red clay tunnel among three alternatives as well as conducts an elaboration and verification of the transformation in the construction way from inclined shaft to main cavity and the adoption of the construction measures.
作者 蒲荣宇
出处 《铁道建筑技术》 2012年第5期1-3,共3页 Railway Construction Technology
关键词 隧道施工 大断面 红黏土 辅助坑道 交叉口 tunnel construction large section red clay auxiliary tunnel intersection