钢桁梁斜拉桥液压顶推滑移关键技术 被引量:5

Key Techniques for Hydraulic Pushing Slip of Cable-stayed Bridge with Steel Truss Girder
下载PDF
导出
摘要 在钢桁梁斜拉桥施工中,由于需要主塔两侧对称拉索来消除拉索对主塔的横向作用力,施工方法通常为首先安装主塔处支架上方钢桁架,然后自主塔两侧对称安装钢桁架。以粉房湾大桥工程钢桁架安装为例,介绍钢桁架斜拉桥支架上方钢桁架液压顶推式累积滑移施工技术。根据墩顶反力和摩擦力,配备4台1 000kN级液压顶推设备。累积滑移最大质量为1 100t,累积滑移距离为52m,采用计算机多点连续动态控制技术进行顶推作业。 In steel truss cable-stayed bridge construction, due to the need for the main tower symmetry and cable to eliminate lasso the main tower of the lateral force, the construction method includes the installation of steel truss above bracket in the main tower, and then symmetry installation of steel truss for the independent tower. Based on installation of steel truss for Powder Room Bay Yangtze River Bridge engineering, the authors introduce construction technology of accumulative sliding with hydraulic pushing for steel truss above bracket about cable-stayed bridge with steel truss. According to the reaction and friction on pier top, four sets of hydraulic pushing equipments with 1 000kN level are equipped. The maximum weight for accumulating sliding is 1 100t, the distance for accumulating sliding is 52m, muhipoint- continuous-dynamic control technology is used for pushing operation.
出处 《施工技术》 CAS 北大核心 2012年第6期6-10,共5页 Construction Technology
基金 中建三局课题(CSCEC3B-2011-23)
关键词 桥梁工程 斜拉桥 钢桁梁 液压顶推 累积滑移 施工技术 bridges cable-stayed bridges steel truss girders hydraulic pushing accumulative sliding construction
  • 相关文献

参考文献6

二级参考文献20

  • 1孙俊啟.郑州黄河公铁两用桥公路箱梁预制场地布置方案研究[J].世界桥梁,2010,38(2):17-19. 被引量:5
  • 2赵英泰,王旭峰.现代空间钢结构高空滑移法施工技术[J].建筑钢结构进展,2006,8(6):11-14. 被引量:25
  • 3张金芝.石太客运专线石咀大桥顶推连续箱梁设计[J].铁道标准设计,2007,27(2):79-81. 被引量:5
  • 4悬索桥.铁道部大桥工程局桥梁科学研究所[M].北京:科学技术文献出版社,1996..
  • 5李和华.钢结构连接节点设计手册[M].北京:中国建筑工业出版社,1993.
  • 6Lu Kekuan.structural design and installation of the whole unit hoising of 1800 ton steel structure of Beijing west railway station[J].Journal of Constructional Steel Research,1998,46 (1):121-126.
  • 7Mokowski Z S,Analysis.design and construction ofdoubly-Layer grid[M].London.Applied science publishers,1981.
  • 8Ding Dajun.Thin,long-span slabs in China[J].Concrete International,1996,18(8):35-38.
  • 9Cuocu D A.Long-span roof structures[J].Modern Steel Construction,1994,34(5):46-50.
  • 10Petersen.J Erection and constructability issues For long-span roofs[J].Modern Steel Construction,1994,34(2):18-24.

共引文献65

同被引文献36

  • 1梁辉,朱东明,曾宪攀,陈玉幸,李勇刚.顶推法架设128m双线简支钢桁梁施工技术[J].铁道标准设计,2012,32(6):54-58. 被引量:14
  • 2方国开.赵寨颍河双线特大桥128m钢桁梁架设浮墩设计[J].铁道建筑技术,2012(S1):1-4. 被引量:2
  • 3侯景德.宣杭铁路复线64m钢桁梁反向拖拉架设施工技术[J].铁道建筑技术,2006(5):11-13. 被引量:3
  • 4张健,胡冲,隋杰明,铁大禹.顶推滑移法在钢结构桥梁安装工程中的应用[J].沈阳建筑大学学报(自然科学版),2007,23(5):764-767. 被引量:13
  • 5JTGD60-2004.公路桥涵设计通用规范[S].[S].,..
  • 6GB/T50017-2003,钢结构设计规范[S].
  • 7Zhang Y,Luo R.Patch Loading and Improved Measures of Incremental Launching of Steel Box Girder[J].Journal of Constructional Steel Research,2012,68(1):11-19.
  • 8Marzouk M,El-Dein H Z,El-Said M.Application of Computer Simulation to Construction of Incremental Launching Bridges[J].Journal of Civil Engineering and Management,2007,13(1):27-36.
  • 9Jiang T Y,Tian Z C,Xu J H.Key Technologies of Whole Incremental Launching Construction Control for Inclined Continuous Box Girder with Steep Longitudinal Gradient[J].Applied Mechanics and Materials,2012,204:2034-2039.
  • 10Wang J,Lin J,Chen C,et al.Simulation Analysis and Control Research of Long Multi-Span Composite Bridge with Incremental Launching Construction[C]//Proceedings of the11th International Conference of Chinese Transportation Professionals.Nanjing,2011:3078-3090.

引证文献5

二级引证文献23

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部