摘要
白云鄂博西矿铁矿尾矿泥和甩尾碎石是矿山选矿厂排放的主要固体废弃物。利用尾矿泥代替砂、甩尾碎石代替级配碎石,采用碾压混凝土工艺进行矿区路面修筑,是改善矿区运输道路路况,延长汽车使用寿命的根本性措施。试验取得了其最佳含水量和最大比重的指标,28 d抗压强度达到18 MPa以上。工业试验路面选择在矿区主运输坡道上,一共做了4块,路面总长66.5 m,宽9.0 m,面积约600 m2,用料量共计165 t。根据路面混凝土芯样强度试验结果,尾矿泥碾压混凝土平均强度在18 MPa以上。
The iron ore tailings mud and gravel drift mine is the main emission solid waste Bayanobo West Mine Concentrator. Tailings mud instead of sand, drift gravel instead of graded gravel, RCC process was adopted in the mine road construction. It improves the mine haulage road traffic, and extends vehicle service life. The trial achieved its optimum moisture content and the largest proportion of indicators, and 28 d compressive strength of more than 18 MPa industrial test road in the mining area on the main transport ramp, a total of 4, the road length of 66.5 m, width 9.0 m, covering an areaabout 600 m2 with feeding amount a total of 165 t - tailings mud the average strength of roller compacted concrete pavement core samples of concrete strength test results, in more than 18 MPa.
出处
《金属矿山》
CAS
北大核心
2012年第6期127-128,共2页
Metal Mine
关键词
尾矿泥
废石
碾压混凝土
路面抑尘
Tailings mud, Waste rock, RCC, Road dust suppressants