摘要
文章以九堡大桥为例,对新型步履式平移顶推施工与传统拖拉式施工方案进行对比分析,创新性地提出采用"步履式平移顶推装置"三跨带拱整体顶推施工工艺,突破了传统的拖拉式施工。确保了九堡大桥顶推施工质量和施工工期。
This paper takes Jiubao Bridge for example to make a comparative analysis of the walking-style horizontal pushing technology and the traditional drag-type construction technology. The innovative use of "walking-style horizontal pushing technology" to install three spans with arches in one process makes a breakthrough of the traditional drag-type construction technology and ensures the quality of the bridge construction and the completion of Jiubao Bridge within the specified construction period.
出处
《中国港湾建设》
2012年第3期67-69,共3页
China Harbour Engineering
基金
浙江省重大科技优先主题项目(2009C11102)
关键词
步履式
拖拉式
顶推
对比分析
walking-style
drag-type
incremental launching
comparative analysis