摘要
辽宁省白石水库前期准备工程概算总投资 172 44万元 .为做好投资控制工作 ,建立了完善的投资控制体系 ,严格审核各承包商月验工计价 .采取了合理分标、优化设计、加强合同管理等投资控制措施 ,从而实现在各项前期准备工程满足设计要求和使用条件下 ,节省工程投资 915万元 。
The estimated investment of primary preparation works of Baishi Reservoir in Liaoning Province is 172.44 million Yuan。To control the investment well, the prefect system was set up。The pricing of monthly work checking of contractors was examined and verified strictly. Some measures for controlling investment, including dividing bids, optimizing designs and strengthening contract management, etc., were taken. There fore, under the condition that all primary preparation works meet the design requirements and use conditions, the project investment of 9.15 million Yuan were saved, and the aim of investment control has been achieved。
出处
《水利水电技术》
CSCD
北大核心
2000年第5期52-54,共3页
Water Resources and Hydropower Engineering
关键词
白石水库
前期准备工程
投资控制
Baishi Reservoir, primary preparation works, investment control