摘要
黄河浪店水源工程属世行贷款山西扶贫项目 ,其建设目的是为了解决长期困扰运城地区的夹马口、小樊、尊村三大泵站的脱流问题。本文从河道特性、河势变化等方面介绍了工程特点 ,指出了本工程的关键问题是工程选址、取水方式以及与三大泵站的关系等问题 ,并围绕这些问题介绍了工程的论证过程。在论证过程中 ,提出了“多口取水”的设计思想 ,同时将目前国内比较先进的泵型用于本工程 ,使工程的实施方案成为在目前技术经济条件下最为合理的方案 ,结合本工程的论证 ,文中对工程论证的重要性及其基本原则。
The characteristics of Langdian Water Project is introduced from the view of river feature and variation of river process.That the site selection,water diversion way,and the relation to existed three pumping stations (Jiamakou,Xiaofan and Zuncun)are three key problems of the Langdian Water Project was pointed out,and the demonstration process around these key problems of Langdian Water Project was introduced in this paper.In the demonstration process,a design thinking of “multi-intake diversion”,that is,diverting water by several intakes besides the Langdian Water Project was presented for the project.Several experiences obtained from the project demonstration and decision are summarized.
出处
《山西水利科技》
2000年第1期36-38,共3页
Shanxi Hydrotechnics
关键词
水源工程
论证
决策
多口取水
选址
泵站
取水
Langdian Water Project Demonstration Site Selection Diversion Way