以江铜瓮福化工有限公司40万吨/年硫酸厂房工程为例,在强夯法处理地基沉降时,对强夯后计算的最终沉降量与实际平均沉降存在的差异提出问题。通过反算,分析造成这一结果的原因,为今后在强夯法处理地基的计算提供参考。
Taking the engineering of sulfuric acid workshop with annual production of 400 thousands tons in Wengfu chemical industry Co. Ltd. , this paper points out the difference of final settlement after forcing ramming and actual average values. It also analyzes the causations through inverse computation to provide reference for the calculation of using forcing ramming to deal with foundation.
出处
《林业科技情报》
2012年第2期67-69,共3页
Forestry Science and Technology Information
关键词
强夯法
沉降量计算
地基处理
结果分析
forcing ramming
settlement calculation
foundation treatment
result analysis