摘要
清江隔河岩水利枢纽导流隧洞出口段为全风化页岩,洞底下为石牌页岩,且系风化层移裂隙发育,是整个隧洞开通困难最大的障碍地段,通过设计、施工人员共同努力与安全监测,工期历时11个月,于1997年12月15日完工过水,创造国内当年开工当年过水的新纪录。
The outlet of the diversion tunnel of the Geheyan project was the most difficult zone to excavate because of the completely weathered shale. with completely weathered Shipai shale underneath the tunnel. and the development of cracks. It took the designers. builders and monitoring engineers 11 months to complete the tunnel on 15 th December. 1997. and thatcreated a new record in China in completing a tunnel in one year.
出处
《大坝观测与土工测试》
2000年第3期36-38,共3页
Dam Observation and Geotechnical Tests
关键词
隔河岩导流隧洞
出口段
围岩变形
安全监测
diversion tunnel
Geheyan Project
outlet section
wall rock deformation
safety monitoring