偏压状态下隧道洞口段明洞暗挖施工 被引量:4

Undercutting Construction in the Open Tunnel for Portal Section with Unsymmetrical Loadings
下载PDF
导出
摘要 山岭重丘区隧道洞口段存在偏压严重现象,需大范围开挖进洞,存在施工安全性差、环境破坏大等问题。利用重力式混凝土偏压挡墙,通过明暗交界段套拱的施作,平衡隧道的单侧偏压力,做到隧道开挖安全进洞。由浙江省宏途交通建设有限公司承建的黄衢南高速公路蕉坞隧道及83省道兰田张隧道,施工中对明暗交界段采取明洞暗挖技术,阐述了偏压状态下隧道明洞暗挖技术原理和技术流程,该技术既确保了隧道的安全施工,又节约了公路建设用地,避免了高边坡开挖,极大地保护了周边原生态环境,同时降低了工程造价,取得了良好的经济和社会效益。 The unsymmetrical loading leading- in tunnel portal is especially serious in high mountains heavy. There are problems of poor construction safety and environmental damage. By gravity concrete retaining wall, the unilateral partial pressure of tunnel is balanced through the umbrella arch to insure security excavation into the hole. The JiaoWu and LanTianZhang tunnel, which were constructed by ZheJiang HongTu traffic construction Co., LTD, take underground cutting technology of cut - and - cover tunnel, With underground cutting technology, the safe construction of tunnel is insured, the highway construction land saved, to avoid the high slope excavation. Furthermore, it greatly protect the surrounding ecological environment, reducing project cost for great economic and social benefits.
出处 《浙江交通职业技术学院学报》 CAS 2012年第2期11-14,共4页 Journal of Zhejiang Institute of Communications
关键词 隧道洞口段 明洞暗挖 偏压状态 效益分析 portal section of the tunnel underground cutting of cut - and - cover tunnel unsymmetrical loading benefit analysis
  • 相关文献

参考文献9

  • 1王梦恕.地下工程浅埋暗挖技术通论[M]合肥:安徽教育出版社,2004.
  • 2丁常国.特大跨超浅埋隧道施工技术[J].地下空间,2002,22(3):214-220. 被引量:17
  • 3AKSOY C O,ONARGAN T. The Role of Umbrella Arch and Face Bolt As Deformation Preventing Support System in Preventing Building Damages[J].Tunnelling and Underground Space Technology,2010,(05):553-559.doi:10.1016/j.tust.2010.03.004.
  • 4JUNEJA A,HEGDE A,LEEFH. Centrifuge Modeling of Tunnel Face Reinforcement Using Fore poling[J].Tunnelling and Underground Space Technology,2010,(04):377-381.doi:10.1016/j.tust.2010.01.013.
  • 5HISATAKE M,OHNO S,KATAYAMA T. Effects of the Ping-Cut Excavation Method on the Restraint of Displacements Ahead of a Tunnel Face[J].Tunnelling and Underground Space Technology,2009,(05):547-554.doi:10.1016/j.tust.2009.02.003.
  • 6FELLINW,KING J,KIRSCH A. Uncertain Modeling and Sensitivity Analysis of Tunnel Face Stability[J].Structural Safety,2010,(06):402.doi:10.1016/j.strusafe.2010.06.001.
  • 7关宝树.隧道工程施工要点集[M]北京:人民交通出版社,2003.
  • 8吴焕通;崔永军.隧道施工组织及管理指南[M]北京:人民交通出版社,2005.
  • 9闫志刚.浅谈隧道安全施工管理及措施[J].山西建筑,2007,33(28):332-333. 被引量:9

二级参考文献2

  • 1中铁十一局五年.重庆市较新线一期工程大坪车站隧道施工组织设计[M].,-..
  • 2田华.现代建筑施工工程安全教育与培训实用教材[M].北京:当代中国音像出版社,2004.

共引文献24

同被引文献12

引证文献4

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部