期刊文献+

包钢热电厂CCPP循环水系统优化运行的研究 被引量:1

Study on Optimal Operations of CCPP Reclaimed Water System in Thermal Power Plant of Baotou Steel
下载PDF
导出
摘要 热电厂为包钢用排水大户,本研究目的是通过试验,了解热电厂CCPP(燃气蒸汽联合循环发电)用排水状况及循环水系统运行状态,根据试验研究提出切实可行的热电厂循环冷却水系统优化运行措施,降低热电厂循环水系统新水用量、排污水量,达到节水减排的目的。 Thermal Power Plant of Baotou Steel is a large household of water consumption and drainage. This study is to understand the conditions of water eonsumption and drainage for gas - steam combined cycle power plant(CCPP) as well as the running state of reclaimed water system through experiments. Based on the experimental study, the feasible measures for optimal operations of circulating eooling water system are proposed as well as the new water consumption and discharge capacity are reduced so that the water could be saved and the emission could be reduced.
出处 《包钢科技》 2012年第3期72-75,共4页 Science & Technology of Baotou Steel
关键词 循环水 药剂 结垢 浓缩倍率 reclaimed water reagent scale concentration ratio
  • 相关文献

参考文献1

  • 1GB50050-2007,工业循环冷却水处理设计规范[s].

共引文献59

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部