摘要
针对 6.5万t aStratco硫酸烷基化装置开工前面临的原料及酸沉积段开工操作问题 ,采取了优化C4加工流程、控制调整乳化液沉积速度等措施 ,从而确保了该装置的顺利开工。
Aiming at the problems of the raw materials and the operation of acid settling stage faced before the start-up of the 65 kt/a Stratco sulfuric acid alkylation plant,the technical measures of C 4 process optimization and emulsion settling rate control were used.The result of start-up proved that these measures were feasible.
出处
《石化技术与应用》
CAS
2000年第2期97-98,共2页
Petrochemical Technology & Application
关键词
硫酸烷基化装置
工艺优化
技术措施
炼油
sulfuric acid alkylation plant
start-up
process optimization
technical measure