期刊文献+

规划变电站的直流偏磁评估 被引量:2

DC Bias Assessment of Planned Substation
下载PDF
导出
摘要 建立规划变电站直流偏磁评估模型,借助潮流计算中的电网数据获取交流电网的直流网络信息。根据该模型开发直流偏磁评估系统,并以规划中的广东惠州220 kV沙逵变电站直流偏磁评估为算例说明该系统的具体应用方法。将该系统应用于广东电网,仿真系统计算值与监测系统测量值的对比结果表明,该评估方法有效。 DC bias assessment model of planned substation is established to obtain data of DC networks in AC power grid by means of grid data in flow calculation. On the basis of this model, DC bias assessment system is developed and the applica- tion method is expounded by the example of DC bias assessment of planned 220 kV Shakui substation in Huizhou, Guangdong Province. The method is used in Guangdong power grid and the comparison between calculated value of simulation system and measured value of monitoring system shows that the assessment method is effective.
出处 《广东电力》 2012年第6期86-90,共5页 Guangdong Electric Power
关键词 直流输电 直流偏磁 仿真计算 评估 DC transmission DC bias simulation calculation assessment
  • 相关文献

参考文献16

二级参考文献131

共引文献398

同被引文献28

引证文献2

二级引证文献44

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部