摘要 头屯河水库放水涵洞作为水库泄流排沙的主要通道,运行多年,工作闸室和明流段底板磨损非常严重。因此,在其抗冲磨加固实践中采用了一级配C40F200W8钢筋混凝土表面铺装球墨铸铁块作为保护层的技术。实践证明,该技术对放水涵洞底板的抗冲磨起到了一定的作用,球墨铸铁块优异的抗冲磨性能也得到了充分体现,为类似水工建筑物的抗冲磨加固提供一定的参考。 As a main discharge and desihing passage, the draw-off culvert of Toutunhe Reservoir Discharge Culvert has operated for many years, of which the bottom slabs of both the working gate chamber and the open-channel section have been seriously abrased. Therefore, a technique for the protection layer, i.e. a kind of reinforced concrete with the grade of C40F200W8 covered by the blocks of nodular cast iron, is adopted for the abrasion--resistance reinforcement. The practice shows that the technique has a certain effect on the abrasion-resistance reinforcement of the bottom slab of the draw-off culvert, while an excellent abrasion- resistant performance of nodular cast iron is fully exerted, and then a certain reference is provided for the abrasion-resistant rein- forcement of the similar hydraulic works as well.
作者 马军
出处 《水利水电技术》 CSCD 北大核心 2012年第7期77-80,共4页 Water Resources and Hydropower Engineering
关键词 球墨铸铁 抗冲磨加固 放水涵洞底板 头屯河水库 nodular cast iron abrasion-resistance reinforcement culvert bottom slab Toutunhe Reservoir
  • 相关文献

参考文献5

  • 1周继扬.球墨铸铁诞生与发展的历史真相[J].现代铸铁,2011,31(4):15-23. 被引量:8
  • 2GB/T 1348-2009,球墨铸铁件[S].
  • 3GB/T50367-2006,混凝土结构加固设计规范[S].
  • 4SL352-2006,水工混凝土施工规范[S].
  • 5DL/T 5169-2002,水工混凝土钢筋施工规范[S].

二级参考文献17

  • 1Loper Carl R Jr.State of the Art of Processing Technology of Ductire Iron Casting [A]. Science and Processing of Cast Iron VIII[C].北京.2006:3-41.
  • 2Piwowarsky.Hochwertiges Gusseisen Springer-Verlag[M].德国哥庭根:斯普林格出版社,1958:209-251.
  • 3F Wust.Stahl und Eisen.1900,20:1040.
  • 4A Ledebur.Stahl und Eisen.1902,22:710.
  • 5Neue Giesserei, T.-W Beihefte.1949,(1):23.
  • 6EPiwowarsky.DRP(德意志联邦共和国)专利:608767,1933.
  • 7EPiwowarsky.DRP(德意志联邦共和国)专利:608767(186),1933.01.17.
  • 8H Morrogh J.Jounal of Iron Steel Institute.1941,143(1):195-207.
  • 9H Morrogh. Production of Nodular Graphite Structure in Gray Cast Iron[J]. AFS Trans., 1948,56:72-90.
  • 10H Morroge,W J Williams. The Production of Nodular Graphite Structures in Cast Iron []Journal Iron Steel Institute, 1948,156: 306-322.

共引文献40

同被引文献12

  • 1SL223-2008,水利水电建设工程验收规程[S].
  • 2GB/T50448-2008,水泥基灌浆材料应用技术规范[S].北京:中国计划出版社.2008.
  • 3DL/T 5169-2002,水工混凝土钢筋施工规范[S].
  • 4SL 303-2004,水利水电工程施工组织设计规范[S].
  • 5SL176-2007,水利水电工程施工质量检验与评定规程[S].
  • 6DTJT5144-2001水工混凝土施工规范[S].
  • 7JC/q986--2005,水泥基灌浆材料[s].北京:中国标准出版社,2005.
  • 8DL/T5169--2002,水工混凝土钢筋施工规范[S].北京:中国电力出版社,2002.
  • 9GB/50367--2006,混凝土结构加固设计规范[S].北京:中国建筑工业出版社,2006.
  • 10马军.头屯河水库放水涵洞底板抗冲磨加固方案及施工技术[J].水科学与工程技术,2011(6):69-71. 被引量:3