摘要
介绍长春客车厂近10km直流供电试验线,该线的牵引变电所设计满足DC750V、DC1500V、DC3000V供电需求,接触网设计要求在同一条走行轨上同时架设柔性接触网和接触轨,满足国内外各种地铁车型的试验条件,同时考虑交流机车引入条件。
The paper introduces the DC power supply test track of about 10 km in Changchun Car Works, the design of the traction substation has met requirements for DC750V, DC1500V, and DC3000V power supply. The catenary design requires both overhead line and contact rail installed on the same track at the same time, satisfying the test conditions of various metro models at home and abroad, and taking into account the conditions of introduction of AC electric locomotives.
出处
《现代城市轨道交通》
2012年第4期4-7,10,共5页
Modern Urban Transit
关键词
试验线
牵引变电所
柔性接触网
接触轨
test track, traction substation, overhead line, contact rail