摘要
该文结合宁波市南外环路东段工程一般路段软土地基处理,介绍塑料套管混凝土桩(简称TC桩)的特点与设计、施工要点,及其与预应力管桩、水泥土搅拌桩等相比在处理效果、工程费用、施工控制等方面的优越性。
The article introduces the characteristic,design and construction gist of plastic sleeve concrete pile(short for TC pile) used in the soft subgrade treatment of the general road section in Ningbo City South Outer Ring road East Section Project,and its superiority in the treatment effect,engineering cost and construction control by compared with the pre-stressed concrete pipe pile,cement mixing pile and etc.
出处
《城市道桥与防洪》
2012年第6期318-322,24,共5页
Urban Roads Bridges & Flood Control
关键词
塑料套管混凝土桩
一般路段
软基处理
工后沉降
沉降观测
plastic sleeve concrete pile,general road section,soft subgrade treatment,settlement after construction,settlement observation