摘要
上海市轨道交通10号线某列检库工程周边环境复杂,根据工程地质条件进行了降水方案设计。通过施工方案的优化,地质挖潜,降水精确控制等措施,在保证基坑安全的同时也保护了环境不受影响。与传统降水方式相比,具有降水时间短,降水总量少,环境影响小的优点。
Because of complicated environment of some depot engineering in Shanghai Rail Transit Line 10, dewatering design is made based on engineering geological conditions. According to measures such as scheme optimization, geological potential tapping and dewatering accurate control, not only the foundation excavation safety is ensured but also the environment is protected. Combined with traditional dewatering methods, the technology has advantages as short dewatering time, little total precipitation and little influence on environment.