地铁车站基坑工程工期风险值计算 被引量:1

Calculation of Construction Period Value-at-Risk of Foundation Pit Engineering for Subway Station
下载PDF
导出
摘要 基于全概率、蒙特卡洛思想,构建阶段工期变化风险值的计算方法与步骤.从工期未发生异常变化、工期发生异常变化但未采取补救措施,以及工期发生异常变化且采取补救措施3方面进行阶段工期变化风险的概率计算,建立了工期异常时间全概率法的计算公式;运用蒙特卡洛思想,构建了基于Matlab的阶段工期变化风险蒙特卡洛法的计算步骤,并将贝塔分布函数用于描述工期变化.最后以某车站基坑工程为例,计算获得了该基坑开挖与支护工期变化风险值,验证了全概率法和蒙特卡洛法的实用性. This paper deals with the calculation methods and the corresponding steps of the value-at-risk due to the construction period change,based on the total probability and the Monte Carlo thoughts.In the investigation,first,the risk probability is calculated for the project without anomalous change during the construction,with anomalous change but without remedial measures,and with anomalous change as well as remedial measures.Based on the probability calculation in the three above-mentioned cases,a calculation formula of full-probability method of abnormal project time is established.Then,by using the Monte Carlo thoughts,the Monte Carlo method calculation steps of the value-at-risk are presented based on Matlab,and the construction period change is described with the Beta distribution function.Finally,with an excavation engineering of a subway station as an example,the value-at-risk during the excavation period and the supporting period is calculated.The results indicate that the full-probability method and the Monte Carlo method are both effective.
出处 《华南理工大学学报(自然科学版)》 EI CAS CSCD 北大核心 2012年第6期139-144,共6页 Journal of South China University of Technology(Natural Science Edition)
基金 国家自然科学基金资助项目(51079052) 广东省交通厅科技项目(200903005) 江苏省普通高校研究生科研创新计划资助项目(CX10B_208Z CXLX11_0437) 河海大学中央高校基本科研业务费专项资金资助项目(2012B03014)
关键词 基坑工程 施工工期 风险估计 风险率 工期风险值 foundation pit engineering construction period risk estimation risk probability construction periodvalue-at-risk
  • 相关文献

参考文献7

二级参考文献51

  • 1陈建峰,胡琪瑛,石振明.砂土地震液化危害的概率分析[J].工程地质学报,2004,12(z1):170-172. 被引量:2
  • 2陈建峰,石振明,唐益群.基于Monte Carlo的砂土地震液化危害概率分析方法[J].地下空间与工程学报,2005,1(1):88-90. 被引量:2
  • 3唐孟雄,赵锡宏.深基坑周围地表任意点移动变形计算及应用[J].同济大学学报(自然科学版),1996,24(3):238-244. 被引量:48
  • 4徐玖平,胡知能,王绥.运筹学(Ⅰ类)[M].北京:科学出版社,2007,9:129-136.
  • 5Bowman R A. Efficient sensitivity analysis of PERT network performance measures to significant changes in activity time parameters[J]. Journal of the Operational Research Society, 2007, 58(10): 1354 1360.
  • 6Meng Q, Wang X B. Sensitivity analysis of logit-based stochastic user equilibrium network flows with entry-exit toll schemes[J]. Computer-Aided Civil and Infrastructure Engineering, 2008, (23): 138-156.
  • 7Cho J G, Yum B J. Functional estimation of activity criticality indices and sensitivity analysis of expected project completion time[J]. Journal of the Operational Research Society, 2004, 55(8): 850-859.
  • 8Elmaghraby S E. On criticality and sensitivity in activity networks[J]. European Journal of Operational Research, 2000, 127: 220-238.
  • 9Demeulemeester H. Project Scheduling: A Research Handbook[M]. Boston: Kluwer Academic Publishers, 2002: 111-112.
  • 10Hershberger J, Suri S. Vickrey prices and shortest paths: What is an edge worth?[C]//Proceedings of the 42nd Annual IEEE Symposium on Foundations of Computer Science, 2001: 253-259.

共引文献233

同被引文献38

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部