摘要
为解决山区单线桥梁清筛换枕施工占用封闭点较多、安全风险较大的问题,根据丰沙线39座桥大规模清筛换枕的施工情况,改进了山区单线桥大修清筛换枕作业程序,并结合清筛换枕所采取的施工方法,提出了清筛换枕施工安全控制措施,在对桥梁结构不进行永久性加固的情况下,完成了清筛换枕施工,从而降低了山区单线桥梁清筛换枕施工的成本,为我国营业线上桥梁的大修施工提供了可借鉴的经验。
In order to solve the problems of various closets and serious safety risks in screen-clearing and pillow-changing construction of mountainous single line bridge, according to the screen-clearing and pillow-changing conditions of 39 large-scale bridges on Fengsha line, the paper improves the screen-clearing and pillow-changing procedures of overhaul bridge construction on mountainous single line, puts forward the safety control measures of screen-clearing and pillow-changing construction. Under the conditions of non-eternal reinforcement of the bridge structure, it finishes the screen-clearing and pillow-changing construction. As a result, it reduces the screen-clearing and pillow-changing cost of mountainous single bridge, which has provided certain guiding value for overhaul construction of domestic operation bridge.
出处
《山西建筑》
2012年第23期218-220,共3页
Shanxi Architecture
关键词
大修施工
清筛换枕
安全控制
overhaul construction, screen-clearing and pillow-changing, safety control