以沈阳市地铁一号线云沈区间土压平衡盾构下穿铁路轨道群工程为例,对施工中采取的技术措施进行了论述,着重介绍了盾构机掘进控制措施和地表沉降控制措施,可为类似工程的施工提供经验。
Taking Shenyang Subway Line One Yun-Shen interval of earth pressure balance shield crossing under the railway track group project as an example,the construction of technical measures are introduced,with emphasis on the boring of shield control measures and surface subsidence control measures,so as to provide valuable reference for the construction of similar engineering.
出处
《铁道建筑技术》
2012年第7期80-82,共3页
Railway Construction Technology
关键词
盾构法隧道
下穿站场铁路
施工技术
shield tunnel
cross under station railway
construction technology