延迟焦化装置转油线改造设计的应力分析

Stress Analysis of Improvement Design of Transfer Line of Delayed Coke Unit
下载PDF
导出
摘要 延迟焦化装置转油线特点是介质处于气液混相状态,温度高、流速快,温降和压力降要求要低,其管道布置是延迟焦化装置管道设计的关键部分。本文通过具体项目的改造设计,采用国际通用应力软件CAESARⅡ对焦化转油线管道应力进行静态分析,总结利用应力分析进行焦化转油线改造设计的要点,并对焦化转油线应力分析简化计算进行了探讨,为往后类似的改造设计的应力分析计算提供参考。 Medium in mixed gas - liquid state, high temperature, fast flow rate and low temperature & pressure drop were the characteristics of coke transfer line of delayed coke unit. The arrangement of the transfer line was the key of the pipeline design of delayed coke unit. This paper summarizes the key points of the transfer line improvement design based on a actual design by using CAESAR Ⅱ stress analysis which was an internationally common software of stress analysis, and a simplified calculation of transfer line stress analysis was discussed for an improvement design of a complex pipeline, which can provide a reference for a similar improvement design in the future.
作者 陈广锋
出处 《广州化工》 CAS 2012年第14期167-169,174,共4页 GuangZhou Chemical Industry
关键词 延迟焦化 转油线 改造设计 应力分析 delayed coking transfer line improvement design stress analysis
  • 相关文献

参考文献3

  • 1中国石化集团洛阳石油化工工程公司.SH/T3219-2002加工高硫原油重点装置主要管道设计选材导则[S].北京:中国石化出版社.2003.
  • 2中国石化工程建设公司.SH/T3041-2002石油化工管道柔性设计规范[S].北京:中国石化出版社,2003.
  • 3张德姜,王怀义,刘绍叶.石油化工装置工艺管道安装设计手册第一篇(第三版)[M].北京:中国石化出版社,2005:522-P522.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部