摘要
采用锚杆静压桩法对一起上部结构已施工的、桩底存在软弱层的桩基事故进行了加固处理,提出补桩桩位与原灌注桩的净距离应保持至少2倍新增桩边长来消除压桩负摩阻力的影响,建议稳压封桩,以减小两种基础间日后可能出现的沉降差。
Anchor jacked pile was used in the reinforcement of a pile foundation accident with structure finished and with soft rock at the bottom of the pile. It' s proposed that the distance between the new pile and the accident pile should be more than twice of the size of the new pile. It' s suggested that sealing pile with the pressure con- stant should be used to reduce the settlement difference between two types of pile.
出处
《广州建筑》
2012年第3期40-42,共3页
GUANGZHOU ARCHITECTURE
关键词
灌注桩
锚杆静压桩
桩基事故
加固处理
cast-in-situ pile
anchor jacked pile
pile foundation accident
reinforcement