项目进度管理方法在三峡升船机工程中的运用 被引量:2

Application of the Project Progress Management Method in the TGP's Shiplift Project
下载PDF
导出
摘要 介绍了进度管理及其控制体系,总结了长江三峡升船机工程进度管理的相关方法、技术及经验。针对三峡升船机复建工程工期紧、交叉作业干扰大、技术质量要求高等特点,以计算机软件为载体,PDCA循环管理模式为基础,ABB矩阵式管理体系为组织,保证了升船机工程进度受控。 Project progress management and its control system are introduced and the related methods, technologies and experiments of the progress management of the TGP's shiplift project are summarized. According to shiplift features char- acterized by tight reconstruction schedule, severely interference during the cross activity and high quality requirements, the control of the shiplift project reconstruction progress can be ensured by the employment of computer software as a car- rier, the PDCA circulation as a foundation and ABB matrix management system as framework.
作者 刘焕
出处 《水电与新能源》 2012年第4期55-57,共3页 Hydropower and New Energy
关键词 进度计划 循环管理 目标控制 三峡升船机 progress schedule circulation management target control the TGP's Shiplift Project
  • 相关文献

参考文献2

二级参考文献2

共引文献5

同被引文献12

引证文献2

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部