摘要
阐述了综掘工作面大坡下山掘进,在遇断层且有淋头水情况下的施工方案设计。经现场实施,顺利通过了此构造断层,为今后掘进工作面通过类似的地质构造提供了设计方案。
The paper explains the construction plan of the deep-slope tunneling on the fully-mechanized tunneling face with faults and drenching water. The plan proves to be effective in tunneling through the faults, which may be of referential significance for the tunneling of the same kind.
出处
《山西科技》
2012年第4期104-105,共2页
Shanxi Science and Technology
关键词
综掘工作面
断层
淋头水
fully-mechanized tunneling face
fauh
drenching water