四川马边200万t/a磷矿选矿厂设计方案探讨

Approach to design scheme of 2 Mt/a phosphate-beneficiation plant in Mabian Phosphate Mine
下载PDF
导出
摘要 四川天瑞矿业马边磷矿在试验基础上,根据下游产品对P2O5品位和MgO质量分数要求,对选别方案进行了技术经济比较,结果表明,在精矿品位满足下游产品要求情况下,采用单一反浮选流程的方案二的经济效益优于采用双反浮选流程的方案一的经济效益。 Comparisons in technical economy were made for the schemes of separation of phosphate ores in Mabian Phosphate Mine of Tianrui Mining Company based on its tests and in light of the requirements from downstream products for P2O5 grade and MgO mass fraction.The results showed that Scheme II-single reverse flotation circuit was better than Scheme I-double reverse flotation circuit in terms of economic benefit under the conditions that the concentrate grade satisfied the requirements of downstream products.
作者 景向阳
出处 《化工矿物与加工》 CAS 北大核心 2012年第8期18-20,共3页 Industrial Minerals & Processing
关键词 磷矿 选矿厂 设计 phosphate rock beneficiation plant design