摘要
在不拆除提升设施的情况下,对煤矿立井井筒进行了组合罐道更换的施工技术研究,该研究优化了临时设施的布置,研究制定了全新的施工工艺,科学合理地组织了施工,缩短了施工时间,保证了施工质量和施工安全,形成了科学的企业施工工法。
The construction technology of combination cage guide replacement was studied for the vertical shaft without demolishing the hoist facilities. On the basis of this research, the arrangement of temporary facilities was optimized, the new construction technology was established, and the construction organization was reasonable, so the construction time was shortened, the quality and safety of construction were ensured, and the scientific enterprise construction methods were formed.
出处
《中国煤炭》
北大核心
2012年第8期83-85,共3页
China Coal
关键词
立井井筒
提升设施
组合罐道更换
施工工艺
vertical shaft, hoist facilities, replacement of combination cage guide, construction technology