焦炭塔空塔气速计算软件及其应用

The Development and Application of the Vapor Velocity Calculation Software on Delayed Coking Drums
下载PDF
导出
摘要 编写了焦炭塔空塔气速计算软件,并利用某装置实际生产数据,分别计算了生焦周期为24 h和20 h两种工况下空塔气速数值。计算结果表明,24 h生焦平均气速为0.1395 m/s,20 h生焦平均气速为0.1494 m/s,该装置实际生产中空塔气速偏大。在空塔气速偏大的情况下,为保证安全生产,焦炭塔内所留安全空高余地过大,从而造成焦炭塔利用系数低。文章最后探讨了提高焦炭塔利用系数的可能性。 The software has been developed to calculate the vapor velocity on delayed coking drums. Based on the operation data of the delayed coking unit, the vapor velocity of two cases has been calculated. For the production cycles of 24 h and 20 h, the average vapor velocity is 0.1395 m/s and 0.1494 m/s respectively. The conclusions have provided that the vapor velocity is larger than the specified value. In order to ensure safety, the empty height is too large in actual production. Thus, the utilization factor of the coke drums is very low. Last, the measures of improving the utilization factor of the coke drums have been investigated.
作者 肖鸿亮 张黎
出处 《广东化工》 CAS 2012年第10期27-28,15,共3页 Guangdong Chemical Industry
关键词 焦炭塔 空塔气速 焦高 空高 生焦周期 coke drum vapor velocity coke height empty height production cycle
  • 相关文献

参考文献1

二级参考文献6

共引文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部