摘要 禹门口提水东扩工程泵站冬季气温低于5℃,针对一级泵站工期紧、任务重等情况,在混凝土施工过程中采用了掺加防冻剂、暖棚法、室内加温等一系列保温措施,取得了良好的施工效果。 The air temperature of constructing Yumenkou Eastern Extension Pumping Station in winter is less than 5℃.In view of the situation that the period to construct the first stage pumping station is pressing and the construction task is heavy , a series of thermal insulation measures during winter season to construct this project's concrete works are adopted . They are adding anti-freezing mixture , heating shed method and raising indoor temperature , and good effect is obtained.
作者 兰欢欢
出处 《山西水利科技》 2012年第3期26-27,共2页 Shanxi Hydrotechnics
关键词 混凝土 冬季施工 保温措施 concrete witer construction thermal insulation measure