700MW机组厂用电切换失败导致机组解列的事故分析及防范措施 被引量:1

Analysis on unit disconnection accident of 700 MW unit caused by switchover failure of auxiliary power and preventive measures
下载PDF
导出
摘要 某电厂700 MW机组并网后厂用电切换失败,1A定子冷却水泵因母线失电故障停运,1B定子冷却水泵虽然自启,但仍然发出定冷水差压低信号,保护动作导致发电机解列。对保护动作原因进行了深入分析,发现了隐患,从联锁保护逻辑优化、更换新型仪表、制订反事故措施等3个方面提出防范措施,有效消除机组运行的安全隐患。 After the 700 MW unit of a power plant had been connected into grid,the auxiliary power switchover had failed;due to the bus voltage loss,the 1A stator cooling water pump was stopped;although the 1B stator cooling water pump started automatically,but the stator cooling water pressure difference low signal had been given out,and protection device had tripped and caused the generator disconnection from the power system.The reason of the protection trip was analyzed in depth;and the hidden dangers were found.Some prevent measures were proposed with 3 aspects of measures such as optimizing the interlock protection logic,replacing the instruments by new type instruments and formulating anti-accident measures;and the safety hidden dangers for unit operation were eliminated effectively.
作者 尹松
出处 《华电技术》 CAS 2012年第8期44-46,48,共4页 HUADIAN TECHNOLOGY
关键词 定子冷却水 解列 联锁控制 厂用电 stator cooling water disconnection interlock control auxiliary power
  • 相关文献

参考文献4

二级参考文献2

  • 1SDJ 279-90电力建设施工及验收技术规范(热工仪表及控制装置篇)[S].
  • 2GUANGDONG ZHUHAI POWER STATION MAINTAIN DOCUMENTS FOR I&C [S]. MITSUBISHI HEAVY INDUSTRIES. LTD, 1996

共引文献36

同被引文献2

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部