摘要
工程量计量是施工管理人员以及预算工作人员进行的日常工作之一,它是合理进行人员、材料调配以及工程价款结算等的基础工作。现浇混凝土构件工程量计量的难点在于构件与构件的界限区划,本文即从一个真实案例入手,论述了现浇钢筋混凝土柱、梁、板工程量的计量方法,以期对施工管理人员、预算工作人员的工作有所帮助。
Measurement of quantities,is one of the daily work of management and budget staff,it is the base of reasonable staff,materials and construction price settlement.Of the difficulty In-situ measurement of quantities of concrete boundaries regionalization lies in the widget and widget,Starting from a real case,this article dealt with in-situ measurement of quantities in reinforced concrete columns,beams,plates,with a view to offer help to offer help to construction management of personnel,budget and staff.
出处
《邢台职业技术学院学报》
2012年第3期79-81,共3页
Journal of Xingtai Polytechnic College
关键词
现浇钢筋混凝土柱
现浇钢筋混凝土梁
现浇钢筋混凝土板
工程量
in-situ reinforced concrete column
in-situ reinforced concrete beam
in-situ reinforced concrete slab
project amount