摘要
结合印尼Jatigede大坝工程现场施工情况,简述了粘土心墙堆石坝高液限粉土砾石心墙施工控制参数的确定过程,提出了高液限粉土砾石防渗心墙的施工控制参数,可为类似工程提供一定的参考。
According to site construction conditions at Jatigede dam in Indonesia,determination of construction control parameters for high liquid limit silty soil and gravel impervious core of rockfill dam with clay core is briefly described.More detail construction control parameters are presented for high liquid limit silty soil and gravel impervious core to provide references for the similar projects.
出处
《四川水力发电》
2012年第4期67-68,79,共3页
Sichuan Hydropower
关键词
堆石坝
高液限粉土砾石防渗心墙
施工控制参数
rockfill dam
high liquid limit silty soil and gravel impervious core
construction control parameters