河床式电站枢纽防渗系统的维修设计一直是水利工程的难点,赵山渡引水工程防渗系统维修设计采用了表面新设止水封闭系统、水下防渗系统检测、防渗墙局部部位上游灌浆堵漏等措施,成功对防渗系统进行了修复和封闭。
Maintenance design for anti-seepage system of power station in river channel is always the difficuhy in hydraulic engineering. Maintenance design for anti-seepage system of Zhaoshandu diversion project adopts surface waterstop system, detection of underwater anti-seepage system and grouting of the upstream of cut-off wall, which maintains the system well.
出处
《中国建筑防水》
2012年第17期26-29,共4页
China Building Waterproofing
关键词
引水工程
防渗系统
维修
补强加固
diversion project
anti-seepage system
maintenance
reinforcement