摘要
简要介绍了美国西屋电站公司的 WDPF- 型集散控制系统的硬件结构及功能结构 ,分析了使用 WDPF- 型集散控制系统构成的太原一电厂 1 3号机组热控系统的情况 ,指出系统调试中出现的一些主要问题 。
It introdues here the hardware structure and function of WDPF Ⅱ DCS system made by westing House Co.and aralyses the I&C part of No.13 Unit in Taiyuan No.1 Thermal Power Plant which is using this system.The main problem occured during the conmmissiong test is presented and correspondier improvement suggestions are raised.