摘要
结合佛岭隧道工程实例,对涌水隧道的处理方法进行了探讨,提出"防、截、排、堵"相结合的治理方法,并采用超前辅助导坑引排涌水、超前注浆方法进行预支护,为同类隧道施工提供技术参考。
Through the project example of Foling tunnel,this paper discussed the treatment methods of gushing water tunnel,put forward the management method combining "prevent,section,row,blocking",and used advanced auxiliary tunnel drained water gushing,advance grouting method for pre-support,provided technical reference for similar tunnel construction.