摘要
施工控制网是建筑施工测量及安装定位精度的基础,合理确定控制网的点位及精度,对保证建设项目的竣工质量及施工速度具有重要意义。秦山核电二期工程是国家重点工程,其测量控制网的建立对工程施工及设备安装质量具有决定性意义。
The construction control network is the basis of measurement and installation of positioning precision. For reasonably determining the network control point and precision is of great significance to ensure the construction project quality and speed of construction. Phase Ⅱ of Qinshan Nuclear Power project is the national key project. Establishment of surveying control network is of decisive significance for the quality of construction and equipment installation.
出处
《资源环境与工程》
2012年第4期394-398,共5页
Resources Environment & Engineering
关键词
秦山核电二期
施工测量
控制网
Phase Ⅱ of project of Qishan Nuclear Power
construction survey
control network