期刊文献+

新建铁路路基上跨既有隧道安全性评估 被引量:20

The Safety Assessment of New Railway Embankment on the Cross-tunnel
下载PDF
导出
摘要 依据福州罗源湾北岸铁路支线疏解线以路基形式近距离上跨既有杭深线飞鸾隧道洞身顶部的工程实例,运用有限差分析数值计算软件FLAC3D进行三维数值模拟分析,研究了新建上跨铁路运营期间列车静载作用下飞鸾隧道结构的安全性及位移的稳定性。研究结果表明运营期间列车静载对下部已有隧道的影响在安全范围之内,为类似工程的修建提供了可靠的参考依据。 Based on the project of North Shore railway extension, Luoyuan Bay, whose Ease-line is in the form of subgrade, on the top of body of the Feiluan Tunnel. Using finite difference numerical analysis software-FLAC3V-dynamic analysis module to analyze the dynamic response of the train, studying the safety of the Feiluan Tunnel structure and the stability of displacement, which is under the static load during the new cross-rail operation, the results show that during the operation, the effects of the train's static load to the lower part exiting tunnel is within the safe range. At the same time, put forward some reliable conclusions and recommendations through the study.
作者 张健
出处 《公路工程》 北大核心 2012年第4期37-39,143,共4页 Highway Engineering
基金 国家自然科学基金资助项目(50908234)
关键词 铁路隧道 上穿 列车静载 数值模拟 安全性评估 railway tunnel upper cross static load of the train numerical simulation safety as-sessment
  • 相关文献

参考文献9

二级参考文献55

共引文献335

同被引文献92

引证文献20

二级引证文献44

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部