摘要 福建闽江大桥工程斜拉桥主塔索导筒采取了以钢骨架为定位基础的关键技术与施工措施,通过"全站仪与CAD软件结合定位精调钢骨架"与"索导筒微调架"等关键技术措施的应用,在保证作业人员安全、施工快捷、技术稳定要求的同时,降低了高塔塔身的施工偏差,符合高精度施工的规范要求。 Combined with the Fujian Minjiang bridge project, introduces the main pylon of cable-stayed bridge cable guide tube in steel frame for positioning based on the key technology and construction measures, Through the" total station and CAD software combined with positioning precision adjustable steel skeleton" and "cable guide tube spinner rack" and a series of key technical measures in application, ensure safety of working personnel, construction of fast, stable technique requirements at the same time, reduce the tower tower construction error, consistent with the high accuracy construction specification.
作者 陈志强
出处 《建筑技术》 2012年第10期887-890,共4页 Architecture Technology
关键词 斜拉桥主塔 索导筒定位 精调 索导筒微调架 cable-stayed bridge main tower cable guide tube positioning fine adjustment cable guidetube spinner rack
  • 相关文献

参考文献2

二级参考文献2

  • 1JGJ104-1997,建筑工程冬期施工规程[S].
  • 2JGJ81-2002.建筑钢结构焊接技术规程[s].[S].,..

共引文献1728

同被引文献8

引证文献2

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部