基于最优控制理论的智能井动态优化技术 被引量:7

Dynamic optimization techniques of smart wells using optimal control theory
下载PDF
导出
摘要 为了最大化油藏价值,以油藏开发周期的净现值最大化为优化目标,建立了智能井生产优化最优控制问题的数学模型;应用最优控制理论中的伴随法计算优化算法所需的梯度值,并结合序列二次规划法,获得最优的生产方案。研究结果表明,与无控制的生产方案相比,优化后的生产方案可使累积产油量增加22.2%,累积产水量下降33.6%,净现值增加了33.2%。 To fully exploit the possibilities of the reservoir,we used net present value (NPV) as the objective function,and established a mathematical model of smart well production optimization,then obtained the optimal control strategy based on sequeneial quodratic programming(SQP). We used adjoint method to calculate the gradients,which were needed for the optimization algorithms. Simula- tions showed that at the end of the production period cumulative oil production is about 22.2% higher than in the reference case, and reduction in cumulative water production is 33.6% ,resulted in an incease of 33.2% in NPV.
出处 《石油学报》 EI CAS CSCD 北大核心 2012年第5期887-891,共5页 Acta Petrolei Sinica
基金 国家重大科技专项(2011ZX05037-001)资助
关键词 生产优化 智能井 伴随法 序列二次规划 净现值 production optimization smart well adjoint method sequential quadratic programming net present value
  • 相关文献

参考文献14

  • 1Gao Changhong,Rajeswaran T. A literature review on smart-well technology[R]. SPE 106011,2007.
  • 2Lorentzen R J,Shafieirad A, Navdal G. Closed loop reservoir manage- ment using the ensemble Kalman filter and sequential quadratic programming[R]. SPE 119101,2009.
  • 3Chen Y,Oliver D S, Zhang D. Efficient ensemble-based closed- loop production optimization[R]. SPE 112873,2008.
  • 4Meum P, Tondel P, Godhavn J M, et al. Optimization of smart well production through nonlinear model predictive control[R]. SPE 112100,2008.
  • 5Alhuthali A H, Datta-Gupta A, Yuen B, et al. Field applications of waterflood optimization via optimal rate control with smart wells[R]. SPE 1 18948,2009.
  • 6Yeten F,, Durlofsky L J, Aziz K. Optimization of smart well con- trol[R]. SPE 79031,2002.
  • 7Brouwer D R,Jansen J D. Dynamic optimization of waterflooding with smart wells using optimal control theory[R]. SPE 78278, 2004.
  • 8Giering R,Kaminski T. Recipes for adjoint code construction[J]. ACM Transactions on Mathematical Software, 1998,24(4) :437-474.
  • 9Li R,Reynolds A C,Oliver D S. History matching of three-phase flow production data[J]. SPE Journal,2003,8(4) :328-340.
  • 10Sarma P, Aziz K,Durlofsky L J. Implementation of adjoint solu- tion for optimal control of smart wells[R]. SPE 92864,2005.

二级参考文献12

  • 1关晓晶,魏立新,杨建军.基于混合遗传算法的油田注水系统运行方案优化模型[J].石油学报,2005,26(3):114-117. 被引量:29
  • 2王大锐.BP世界能源统计(2005版)[J].石油勘探与开发,2006,33(1):98-98. 被引量:1
  • 3方涵先,王廷芳,黄思训,杜华栋.变分伴随方法应用于大气化学初值和参数反演研究[J].南京气象学院学报,2007,30(2):216-223. 被引量:7
  • 4Lien M, Brouwer D R, Manseth T, et al. Multiscale regularization of flooding optimization for smart field management [ R]. SPE 99728,2006.
  • 5Przyhysz-Jarnut J K, Hanea R G,Jansen J D,et al. Application of the representer method for parameter estimation in numerical reservoir models[J]. Computational Geosciences, 2007, 11 ( 1 ) : 73-85.
  • 6Naus M M J J,Dolle N,Jansen J D. Optimization of commingled production using infinitely variable inflow control valves[R]. SPE 90959,2006.
  • 7Horsup D I. A breakthrough technology for maximizing water injectivity and asset integrity[R]. SPE 108675,2007.
  • 8Aziz K, Settari A. Fundamentals of reservoir simulation [M]. New York : Elsevier Applied Science Publishers, 1986 : 102-103.
  • 9Brouwer D R, Jansen J D, Van der Starre S, et al. Recovery increase through water[looding with smart well Teehnology[R]. SPE 68979,2004.
  • 10Sarma P, Durlofsky L J, Aziz K. Efficient closedloop production optimization under uncertainty[R]. SPE 94241,2005.

共引文献35

同被引文献105

引证文献7

二级引证文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部