摘要 江滨大厦续建工程,由于上部建筑方案改变,整体计算结果表明续建后部分框架柱柱底内力大于原设计并已施工完成桩基竖向承载力。根据地质勘察资料和工程试验报告,本工程采取后注浆处理方法,改善桩端持力层岩土力学性能,提高单桩竖向极限承载力的同时满足设计要求。 For the architectural designing change of JiangBin Building,the calculation analysis of extending costruction project indicated the short of vertical capacity of some existed piles.According to the geological survey and engineering tested report,this project adopted post grounting to improve mechanical properties of soil layer in bearing stratum of pile tip.Besides satisfying the design requirement,it enhanced the ultimate vertical bearing capacity of a single pile.
作者 许春
出处 《福建建筑》 2012年第9期81-82,共2页 Fujian Architecture & Construction
关键词 桩基础 后注浆 单桩竖向极限承载力 Pile foundations Post grounting Ultimate vertical bearing capacity of a single pile
  • 相关文献

参考文献3

  • 1江滨大厦续建工程单桩竖向抗压静载测试试验报告[R].南昌市江西省煤矿设计院.2009.8.
  • 2JGJ 94-2008,建筑桩基技术规范[S].
  • 3JGJ8-2007,建筑变形测量规范[S].

共引文献1296

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部