南水北调中线典型渠段施工期降水措施研究 被引量:3

Dewatering Measures for Construction Period of the Typical Canal Stretch of Middle Route Project of SNWT
下载PDF
导出
摘要 针对南水北调中线工程陶岔—沙河南段施工期地下水问题,选取典型断面建立渗流数值模型,计算分析有、无降水措施及不同计算条件下基坑的渗流场分布特征.研究结果表明,对于存在承压水的基坑工程,当基坑开挖深入地下水位以下且随着含水层顶板减薄,基坑底部易出现安全问题,应采取渗流调控措施;施工期补给边界、含水层厚度及其渗透性、降水井布置等因素对基坑降水效果的影响显著. The groundwater is an important factor for the safety of foundation pit. In order to analyse the distri- bution of seepage field under different calculating conditions with seepage control measures, a typical canal stretch was modeled for construction period of Middle Route Project of SNWT. The numerical simulation re- sults show that the pit safety would decrease with the less permeable layer being excavated step by step and aq- uifer confined beneath it, so measures should be taken to control and regulate the seepage field. The efficiency of foundation pit dewatering would be affected by the water recharge boundary, the thickness and permeability of the aquifer, the arrangement of dewatering wells, and so on.
出处 《郑州大学学报(工学版)》 CAS 北大核心 2012年第5期82-86,共5页 Journal of Zhengzhou University(Engineering Science)
基金 国家"十二五"科技支撑计划资助项目(2011BAB10B04) 国家大坝安全技术研发中心资助项目(2011NDS003) 中央级公益性科研院所基本科研业务费资助项目(CKSF2010017)
关键词 南水北调中线 基坑降水 渗流场 south-north water transfer project foundation pit dewatering seepage field
  • 相关文献

参考文献4

  • 1中国建筑科学研究院.JGJ120-99建筑基坑支护技术规程[S].北京:中国建筑工业出版社,1999.
  • 2MC DONALD MG,HARBAUGH AW. MODFLOW:模块化三维有限差分地下水流动模型[M].郭卫星,卢国平,译.南京;南京大学出版社,1998.
  • 3丁金华,陈劲松.南水北调中线工程汉江兴隆水利枢纽初步设计阶段围堰渗流控制措施及基坑降水措施研究报告[R].武汉:长江科学院,2006.
  • 4王金龙,崔皓东,张家发.南水北调中线陶岔-沙河南典型渠段施工期降水研究[R].武汉:长江科学院,2010.