吉林台一级水电站大坝施工导流围堰技施设计 被引量:1

Detail design of diversion cofferdam in dam construction for JilintaiⅠhydropower station
下载PDF
导出
摘要 文章根据工程的水文特点、自然条件、地质地形条件、当地材料等,结合导流方式和工程要求,施工期大坝围堰不仅承担施工导流挡水任务,同时还要满足工程施工期度汛100年重现期洪水的挡水要求。并简要介绍了大坝施工导流土石围堰的标准选择、断面形式和基础处理设计,为类似水电工程的施工导流围堰设计提供一定的实践经验和借鉴。 Based on the project hydrology characteristics,natural condition,geological and topographical conditions,the local materials,and so on,combining with the diversion mode and the project requirement,the cofferdam in dam construction period not only undertakes construction diversion and water retaining task,but also meets water retaining requirement when one percent frequency flood happens in project construction.The paper introduces briefly the standard selection,cross section and foundation treatment design of the diversion earth-rock cofferdam in dam construction,which has reference for the similar projects.
出处 《东北水利水电》 2012年第10期6-8,71,共3页 Water Resources & Hydropower of Northeast China
关键词 大坝施工 导流围堰设计 吉林台一级水电站 dam construction diversion cofferdam design Jilintai cascade Ⅰhydropower station
  • 相关文献

同被引文献5

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部