海洋修井机改造工程实施方案分析及经验总结 被引量:8

Implementation Scheme Analysis and Experience Summary of Offshore Workover Rig Modification Project
下载PDF
导出
摘要 海洋修井机总体设计均为模块式,可搬迁应用于不同平台。中海油CB-B平台原K400修井机已经报废拆除,需要新配置一套大吨位海洋修井机实施调整井作业。HXJ180MB海洋修井机为机动设备,作业能力强,将HXJ180MB海洋修井机安装应用到CB-B平台上,需要解决多方面的技术问题,因为海洋石油生产平台的井口区设置及接口设计均各有特征,所以使得海洋修井机适应性改造工程变得复杂。文章通过对中海油渤海油田CB-B平台安装HXJ180MB海洋修井机实施方案的分析,总结了该类工程的特征和一系列技术问题的解决方案。因该工程改造内容全面,具有普遍代表性,可供同类型工程参考。 In general design,the offshore workover rig is a kind of movable modular structure and thus could be used in different platforms.The original K400 workover rig on Bohai CB-B platform of CNOOC was discarded as useless,so a new heavy workover rig HXJ180MB was installed on the CB-B platform.Because the wellhead zone layout and interface designs of platform had different features,the adaptive modification of the workover rig was complicated.This article summarizes the characteristics and solutions of such project by analyzing the implementation scheme of installing HXJ180MB movable workover rig on the CB-B platform.Because this modification project covered all the adaption or modification work on rig and platform and was typical,it could be an example for similar projects.
出处 《石油工程建设》 2012年第5期11-16,5,共6页 Petroleum Engineering Construction
关键词 海上平台 海洋修井机 升级改造 offshore platform offshore workover rig upgrading modification
  • 相关文献

参考文献4

二级参考文献4

共引文献49

同被引文献36

引证文献8

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部