摘要
通过马钢股份公司一铁总厂高炉冲渣循环水设施冲渣水池的设计,按照地下存在,水池需满足抗浮要求,计算出水池底板和配筋;以及在水池中设置泄水孔,不考虑水池抗浮,从而选取合理方案,达到节约大量工程资金的目的。
Through a general ironmaking plant of Maanshan Iron Steel Co.of blast furnace slag recycled water facilities in slag pool design,according to the existed underground,pool needs to meet the requirements of anti-floating,calculate the pool bottom and reinforcement;and set hole in the sink,not considering pool anti-floating,in order to select a reasonable solution to save a lot of project funds.
出处
《安徽冶金科技职业学院学报》
2012年第4期8-9,20,共3页
Journal of Anhui Vocational College of Metallurgy and Technology