海底隧道断层破碎带信息化施工

Information construction of the subsea tunnel in a fault and crush zone
下载PDF
导出
摘要 海底隧道开挖支护施工难度很大、安全风险极高,结合国内第二条海底隧道断层破碎带施工。采用地质调查、隧道地震勘探法(TSP法)、隧道内超前钻孔等方法,通过数据分析处理,预测了掌子面前方45 m范围内的基本地质条件,如岩性、规模、位置的长期超前地质预报,以及精度较高的短期超前地质预报,据此综合超前地质预报结果,采取上半断面全断面超前预注浆加固地层、台阶法开挖、加强支护。同时,对施工中水平收敛、拱顶下沉等监控量测数据进行分析,动态反馈于施工过程中,此即海底隧道断层破碎带信息化施工。该方法在施工中取得令人满意的结果。 The construction of the excavation and support of the subsea tunnel is very difficult,and safety risk is also very high.Relying on the construction of a fault and crush zone of the second subsea tunnel inland,using the method of geologic survey,TSP,flank holes,and analyzing the data,predicting basis geology condition within 45 meters ahead of working face.Combining long-term geology prediction with short-term geology prediction,comprehensive pre-geology prediction is reported.According to its geological property,adopting full sectional grouting upper section in the fault and crush zone in order to strengthen stratum,bench excavation method,and strong support.At the same time,monitoring and measuring convergence,subsidence of crown,and pressure of surrounding rock,by processing of data,and to the construction,is called the information construction of the subsea tunnel in a fault and crush zone.The method is applied to the construction,produces a satisfactory effect.
出处 《中国工程科学》 北大核心 2012年第10期57-64,共8页 Strategic Study of CAE
关键词 海底隧道断层破碎带 综合超前地质预报 超前预注浆 信息化施工 a fault and crush zone of subsea tunnel comprehensive pre-geology prediction full sectional grouting information construction
  • 相关文献

参考文献7

  • 1覃仁辉,王成,杨其新.隧道工程[M].重庆-乌鲁木齐:重庆大学出版社-新疆大学出版社,2001.
  • 2祁生文,伍法权,兰恒星.盘石头水库泄洪洞、导流洞进出口高边坡稳定性分析[J].岩石力学与工程学报,2002,21(3):353-359. 被引量:15
  • 3苏华友,杨有玉.隧洞施工中围岩收敛观测及分析[J].中国矿业大学学报,2002,31(2):198-200. 被引量:14
  • 4Najm K, Ishijima Y. Back analysis of tunnel lining deformation: Development and application of passive resistance method [ J ]. Rock Mechanics and Rock Engineering, 1993,26 (1):71 -79.
  • 5Tonon F, Amadei B. Effect of elastic anisotropy on tunnel wall displacements behind a tunnel face [ J]. Rock Mechanics and Rock Engineering,2002,35 (3) : 141 - 160.
  • 6Oda M, Yamabe T, Ishizuka Y, et al. Elastic stress and strain in jointed rock masses by means of crack tensor analysis [J]. Rock Mechanics and Rock Engineering, 1993,26 (2) :89 -112.
  • 7Nie X, Zhang Q. A system of monitoring and dimensioning tunnel support [J]. Rock Mechanics and Rock Engineering, 1994, 27( 1 ) :23 -36.

二级参考文献12

共引文献27

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部