新建铁路铺架基地设置方案的选择与确定,是保证线路铺架工程顺利开展的关键,也是工程设计施工组织设计中重要工作内容之一。此文以蒙西铁路拟设靖边东站铺架基地为例,阐述铺架基地的设置原则及特点,并对通过现场勘察提出的5种设置方案,从大临工程费用和满足总工期要求角度进行分析与比较,最终根据全线典型的总工期控制工程确定设置方案五。
the new railway paving frame base design scheme selection and determination, is the key of guaranteeing line paving frame project smoothly carrying out, is also one of the important work content of engineering design construction organization design. Taking MengXi railway setting JingBianDong station paving frame base as an example, this paper expounds paving frame base setting principles and characteristics. And the five kind of design scheme put forward by field survey are analyzed and compared from the project requirements of the engineering cost and satisfying the total time limit. Finally, according to the typical total time limit control, design scheme five is determined.