摘要
通过10 kV出线间隔额定配置,对变电站主变和出线之间匹配情况进行了分析和计算,得出了一些对管理有帮助的数据,并据此对提高10 kV出线间隔工效做了初步探讨。
According to rating configuration of 10 kV transmission bays, analysis and calculation on matching between main transformer and transmission lines were given. And discussion on promotion of work efficiency for 10 kV bays was put forward based on data helpful for management which was obtained from analysis and calculation.
出处
《华北电力技术》
CAS
2012年第10期28-30,共3页
North China Electric Power